Electricity and gas supplies installed to houses and sewage lift pumps, and construction started on the stone front boundary wall
Plots 1&2: Walls and ceilings plasterboarded and plot 2 skimmed. First fix electrical completed and staircase installed to plot 1
Plots 3&4: Heating systems commissioned. Wall boards fitted in bathrooms