Pow Wood Progressing!

Good progress has been made in the past month and the water supply for all houses has been installed by United Utilities

Block work for Plots 1&2 has progressed well – first floor joists installed and flooring and blockwork continuing to roof level

Internal studwork for Plots 1&2 has been completed

… and first fix electrical work is in progress